Sharing a quick reference productivity sheet for various construction activities. This helps in planning, estimating labor requirements, and improving site efficiency. πŸ‘·β€β™‚οΈπŸ“Š
(plz note : some units in the shared image were incorrect, please refer below details for accurate refrence)
πŸ”Ή Excavation & Earthwork
• Manual Excavation βž” 1.5 – 2.0 m³ per labour/day
• By JCB βž” 60 – 80 m³ per hour
• By Poclain (200) βž” 100 – 150 m³ per hour
• Roller Compaction βž” 200 – 250 m³ per day
πŸ”Ή Concrete Works
• Manual Mixing βž” 1.5 – 2.0 m³ per labour/day
• Manual Laying βž” 3 – 4 m³ per labour/day
• Placement by Pump βž” 20 – 30 m³ per hour
• Curing (Ponding) βž” 1 labour per 100 m²
• Shuttering βž” 1.2 – 1.5 m² per labour/day
πŸ”Ή Reinforcement Work
• Cutting, Bending, Tying βž” 100 – 150 kg per labour/day
• Fixing (Columns/Beams) βž” 80 – 120 kg per labour/day
• Fixing (Slabs/Footings) βž” 100 – 150 kg per labour/day
πŸ”Ή Masonry
• Brick Masonry (Manual) βž” 0.2 – 0.25 m³ per labour/day
• Brick Masonry (Machine Mixing) βž” 0.3 – 0.4 m³ per labour/day
• AAC Block Masonry βž” 0.5 – 0.7 m³ per labour/day
πŸ”Ή Plastering & Finishing
• 12mm Plaster βž” 8 – 10 m² per labour/day
• 20mm Plaster βž” 6 – 8 m² per labour/day
• Putty βž” 12 – 15 m² per labour/day
• Painting (1 coat) βž” 15 – 20 m² per labour/day
• Tiling βž” 3 – 4 m² per labour/day
πŸ”Ή Road & Paving
• PCC (Manual Mixing) βž” 1.5 – 2.0 m³ per labour/day
• Asphalt Laying βž” 25 – 30 m² per labour/day
• Kerb Stone βž” 30 – 40 m per labour/day
• Paver Block βž” 5 – 7 m² per labour/day
βœ… A helpful guide for quantity estimation, productivity planning, and monitoring progress on-site.
πŸ“Œ These values serve as general guidelines. Actual productivity may vary based on site conditions, labour skill, weather, and equipment used.