Civil Engineering HELP

Sharing a quick reference productivity sheet for various construction activities. This helps in planning, estimating labor requirements, and improving site efficiency.
(plz note : some units in the shared image were incorrect, please refer below details for accurate refrence)
Excavation & Earthwork
• Manual Excavation β 1.5 – 2.0 m³ per labour/day
• By JCB β 60 – 80 m³ per hour
• By Poclain (200) β 100 – 150 m³ per hour
• Roller Compaction β 200 – 250 m³ per day
Concrete Works
• Manual Mixing β 1.5 – 2.0 m³ per labour/day
• Manual Laying β 3 – 4 m³ per labour/day
• Placement by Pump β 20 – 30 m³ per hour
• Curing (Ponding) β 1 labour per 100 m²
• Shuttering β 1.2 – 1.5 m² per labour/day
Reinforcement Work
• Cutting, Bending, Tying β 100 – 150 kg per labour/day
• Fixing (Columns/Beams) β 80 – 120 kg per labour/day
• Fixing (Slabs/Footings) β 100 – 150 kg per labour/day
Masonry
• Brick Masonry (Manual) β 0.2 – 0.25 m³ per labour/day
• Brick Masonry (Machine Mixing) β 0.3 – 0.4 m³ per labour/day
• AAC Block Masonry β 0.5 – 0.7 m³ per labour/day
Plastering & Finishing
• 12mm Plaster β 8 – 10 m² per labour/day
• 20mm Plaster β 6 – 8 m² per labour/day
• Putty β 12 – 15 m² per labour/day
• Painting (1 coat) β 15 – 20 m² per labour/day
• Tiling β 3 – 4 m² per labour/day
Road & Paving
• PCC (Manual Mixing) β 1.5 – 2.0 m³ per labour/day
• Asphalt Laying β 25 – 30 m² per labour/day
• Kerb Stone β 30 – 40 m per labour/day
• Paver Block β 5 – 7 m² per labour/day
A helpful guide for quantity estimation, productivity planning, and monitoring progress on-site.
These values serve as general guidelines. Actual productivity may vary based on site conditions, labour skill, weather, and equipment used.
Aug 10,2025